Augmentation of Dust Extraction Capacity

PERIOD : 2016-2017
LOCATION : Contrecoeur (Quebec, Canada)

Project Outline

Installation of two dust extraction systems and a ventilation tower at the Contrecoeur West steel mill. The equipment installed in this project was recovered from another plant at the same site. Groupe Alphard were commissioned to undertake the preliminary engineering required to produce site planes and quotations in preparation for a call for bids for the completion of the works.


  •  Mechanical engineering (sizing, production of general plans, quotes for decommissioning and recovery, etc.);
  •  Structural and Civil engineering (foundations, support structures, etc.);
  • Electrical engineering, instrumentation and control (power checks, cable trays, CCM, lighting, grounding);
  • POV preparation and monitoring, commissioning support